Niron Magnetics will build a $1.8 billion, 10,000-ton magnet plant in Alabama after Minnesota lost out on power capacity and incentives. CEO Jonathan Rowntree targets ten plants worldwide.

Surveyed
November 22, 2026
Reading
4 min read
Correspondent
Amara Osei
Niron Magnetics Picks Alabama for New $1.8 Billion, 10,000 Ton Facility
Niron Magnetics Picks Alabama for New $1.8 Billion, 10,000 Ton Facility — invisibleai / pixabay

Field notes

  1. Niron Magnetics announced a $1.8 billion second facility in Alabama on November 20, producing 10,000 tons of magnets.
  2. Minnesota was a finalist but lost on incentive packages and access to several hundred megawatts of power.
  3. Niron currently produces about 1,000 magnets per day in Northeast Minneapolis; Sartell Plant One opens in 2027.
  4. US magnet consumption is about 50,000 tons per day; global demand is expected to triple in a decade.
  5. CEO Jonathan Rowntree plans up to ten plants, including future sites in Europe and Southeast Asia.

Niron Magnetics will invest $1.8 billion in a second US manufacturing facility in Alabama, Governor Kay Ivey's office announced on November 20. The plant, which the company calls "Plant Two," will produce approximately 10,000 tons of rare-earth-free magnets, compared with the 1,500 tons planned at Plant One in Sartell, Minnesota.

The decision ends a site-selection contest in which Minnesota, Niron's home state, reached the final five but lost on incentives and electricity. Niron, spun out of University of Minnesota research and headquartered in Minneapolis, currently produces around 1,000 magnets per day in Northeast Minneapolis. Its Sartell facility is scheduled to come online in 2027.

What does the scale of demand look like?

The United States consumes roughly 50,000 tons of magnets per day, and the world consumes about 300,000 tons, according to figures cited by the company. Global demand for magnets is expected to triple over the next decade. Niron's technology produces high-performance magnets without rare earths (critical minerals used in conventional permanent magnets), positioning the company to supply that growth.

CEO Jonathan Rowntree framed Plant Two as the moment Niron materially affects domestic supply. "Plant Two is 10,000 tons, where we move the needle on reliably supplying the U.S. market," Rowntree said.

Why did Minnesota lose the plant?

In a mid-October interview, Rowntree said Minnesota remained a finalist but faced structural disadvantages. He cited higher construction costs and incentive packages unlikely to close the gap with competing states.

"We're down to five states, five sites. We still got Minnesota in the mix, but they're struggling to be competitive on incentive packages, and we've still got some challenges on power," Rowntree said.

Power emerged as a decisive factor. "We need several hundred megawatts of power. So it's not data center level, but it's not a small chunk of power," he said. Few available sites offer that capacity ready to build on, and Rowntree indicated other states could deliver the required scale of electricity faster.

The Alabama site offered concrete logistical advantages. It features direct CSX rail access, and the state of Alabama prepared the site so construction can begin immediately. Rowntree also flagged the financing environment: "This is more than a billion-dollar kind of project. And so that's why we need support to help with cost-effective loans, especially in this current environment where interest rates have come up." Final numbers on the Alabama incentive package have not been disclosed.

Was the expansion always the plan?

Signs of the move surfaced weeks before the announcement. Two weeks ago, Niron opened an Experience Center in Northeast Minneapolis showcasing its magnets in an electric motorcycle, high-end speakers, motors and e-bikes. At that event, Rowntree emphasized the company's Minnesota identity.

"Niron's home is Minnesota. Our headquarters is Minnesota," he said — a signal that manufacturing would expand elsewhere while the head office stays put.

In an interview this spring on The Twin Cities Business Show, Rowntree had already outlined ambitions beyond US borders: "The sky's the limit, to be honest, with our technology. We have plans to build a number of high-volume manufacturing plants… We may build more plants here in the US, but we'll also have a very heavy export business. So we are also considering future plants both in Europe and in Southeast Asia."

Where does Niron go from here?

Plant One in Sartell was designed as a replicable template rather than a one-off facility, and Plant Two applies that model directly.

"There's no more scaling after Plant One. It's really copy and paste. So we take the largest line in Plant One and just copy that multiple times and paste it in Plant Two," Rowntree said.

On the Twin Cities Business Show in April, he set the long-term target: "We're really focused right now on plant one and plant two, but fully intend that we're going to hopefully build that through plant one through ten."

For Minnesota, the announcement cuts both ways: a homegrown company scales toward a ten-plant global footprint, while its largest single investment lands in Alabama.

via tcbmag.com (Source)

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Market editor covering people, launches and day-to-day practice in corporate strategy and chief-executive leadership at CEO Frontier.

552 articles

Filed under

Adjacent sheets

« Previous articleNext article »

End of sheetNovember 22, 2026