U.S. Could Run Short of Grid Transformers as Early as Next Year
A Johns Hopkins study warns copper runs short next year, transformer gaps hit 15% by 2029, and wait times have hit two years as AI demand strains the U.S. grid.
- Grid
- N-19 / Q4
- Surveyed
- November 20, 2026
- Reading
- 4 min read
- Correspondent
- Priya Raman

Field notes
- Johns Hopkins study: U.S. transformer and converter shortages begin as early as next year and turn acute by 2030.
- High-demand scenario: ~15% transformer shortfall and 30% shortage of other grid equipment over four years; a 70% trade disruption widens gaps to 25% and 36%.
- U.S. power demand projected to climb 21% by 2030; data centers could drive two-thirds of the equipment shortfall.
- JPMorganChase estimates the grid needs ~$1 trillion in investment through 2035; DOE committed $1.9 billion to 31 projects in September.
- Transformer lead times quadrupled in four years, from six months to over two years; only one U.S. mill makes grain-oriented electrical steel.
The United States could start running short of the transformers and converters that connect power plants and data centers to the grid as early as next year, according to a Johns Hopkins University study published in Cell Reports Sustainability. The researchers project shortages will turn acute by 2030, and the stakes are enormous: JPMorganChase separately estimates the U.S. grid needs roughly $1 trillion in investment through 2035.
The timing is brutal. A string of technology failures this past week grounded flights, delayed bank transactions and knocked out email for millions of Americans, pushing infrastructure vulnerabilities into the open. The grid's own weak spot, it turns out, is made of copper and steel.
For businesses and households, the likely consequences are higher electricity bills and more frequent power outages.
"This type of equipment was taken for granted but without it, you can build a data center or a power plant but it won't be powered because you cannot connect it to the grid," Yury Dvorkin, a Johns Hopkins associate professor who conducted the study with PhD candidate Boyu Yao, said in a university release. "When the demand for electricity started to grow faster than expected, it started to amplify all the cracks in the industry."
Why is demand suddenly outrunning supply?
U.S. power use historically grew about 1% to 2% a year. The study projects it will climb 21% by 2030 as AI data centers, electric vehicles and broader electrification pile on. Data centers alone could account for as much as two-thirds of the expected equipment shortfall. Over the longer run, the National Electrical Manufacturers Association projects U.S. electricity demand will grow more than 50% by 2050.
The grid wasn't built for that surge. More than 70% of U.S. transmission lines are over 20 years old, according to Columbia Business School, and utilities need years to build and connect the capacity AI developers want right now.
Which materials run out first?
Transformers and other grid hardware rely on copper, steel, nickel, aluminum and manganese. The researchers found the U.S. risks running short of all five within the next four years:
- Copper comes first, as early as next year — and the ripple effects reach well beyond the grid, hitting data center equipment, converters for wind power and EV charging infrastructure.
- Steel and nickel follow, and will be nearly impossible to source by 2030.
How big are the gaps?
The numbers depend on the scenario:
- If demand stays high, the U.S. will be almost 15% short on transformers and 30% short on other critical grid equipment over the next four years.
- Add a trade disruption, modeled as up to a 70% drop in materials from unstable trading partners, and the transformer gap widens to about 25%, with a 36% shortage of everything else.
- Even if demand growth is modest, the country would still come up about 16% short on other grid-supporting equipment, though transformer supply would hold.
Why can't manufacturing just scale up?
Money is moving, but slowly. In September, the Department of Energy committed $1.9 billion to 31 projects meant to squeeze more power out of existing lines and lower costs. That's a fraction of what's needed against JPMorganChase's $1 trillion estimate through 2035.
Part of the bill is replacement. Much of the grid is aging out, and old transformers need refurbishing or replacing — competing for the same scarce supply as new projects. Rising upkeep costs are already showing up in Americans' utility bills.
Manufacturing itself is the bottleneck. Transformers are typically custom-built, and lead times have quadrupled in four years, from about six months to more than two years. Large power transformers also depend on grain-oriented electrical steel (a specialty alloy aligned for minimal energy loss), which only one U.S. mill produces.
What fixes do the researchers propose?
The study points to three measures that could stretch existing supply:
- Low-cost sensors that monitor transformer loads in real time.
- Recycling materials from retired units.
- More standardized designs, so one transformer can stand in for another.
Until supply catches up, access will come down to money. "Utilities will compete for transformers with the data center industry," Dvorkin said. "Transformers will first be delivered to whoever can pay the highest premium. Will it be a mom-and-pop utility or a big data center corporation?"
That question will define who keeps the lights on — and who pays for the privilege.
via fortune.com/feed/ (Source)
More from Priya Raman
Show full bio
Senior reporter covering technology and product news in corporate strategy and chief-executive leadership at CEO Frontier.
508 articles
Adjacent sheets
- Data Centers Need Community Stakes and Regulatory Accountability
- Senate Bill 62-33 Makes Big Tech Pay Its Own Grid Bill
- Restricting Data Centers Is a Strategic Mistake: The Case for Building Megawatts
- Home batteries could bridge the data center power crunch
- Why Grid Operators Cut Power on Purpose: Inside Rolling Blackouts