Centrus Energy carries a $7bn order book to 2040 and $2.24bn in cash, but Q3 revenue fell to $55.5m, DOE funding for an $800m backlog line is absent, and the Piketon lease expires in 2027.
- Surveyed
- November 28, 2026
- Reading
- 5 min read
- Correspondent
- Sophie Lindqvist

Field notes
- Centrus signed a final HALEU agreement with Oklo on 11 November, with two prepayments totaling $35 million
- Order book stood at $7 billion as of 30 September, but only $5.1 billion sits under final agreements
- Q3 revenue fell to $55.5 million from $74.9 million; adjusted net loss was $9.4 million
- DOE's proposed FY2027 budget omits funding for the current HALEU cascade contract, which carries about $800 million of backlog
- Piketon lease expires 1 October 2027; DOE is not obligated to sign an extension
Decision first: $7 billion booked, but only part of it is firm
Centrus Energy holds a $7 billion order book running to 2040 — and that single figure, quoted as of 30 September, frames both the promise and the problem. About $5.4 billion of it represents conditional LEU and HALEU sales (LEU is low-enriched uranium, the standard fuel for today's reactors; HALEU is high-assay low-enriched uranium, a fuel for advanced designs). Only $5.1 billion sits under final agreements, and even that depends on the company actually building and commissioning new production capacity on schedule.
The market, for its part, has already voted. LEU shares fell roughly 75.3% from the January high of $345.60 to $85.43. What does this change for investors? It separates the contract-announcement phase of the nuclear fuel story from the delivery phase — and Centrus has not yet proven the second one.
Is the AI demand story real yet?
Partially, and with money attached. On 11 November Centrus signed a final HALEU supply agreement with Oklo, the advanced-reactor developer, covering enrichment services for 2029-2031 on take-or-pay terms (the buyer pays whether or not it takes delivery). Oklo committed two prepayments totaling $35 million, credited against future fuel purchases.
A second strand ties into the Meta buildout. Under a 30 September agreement connected to Oklo's energy project for Meta in Ohio, the first Meta tranche was released from escrow on 2 November and paid directly to Centrus against future fuel orders. Oklo's Ohio campus is designed for 1.2 GW and intended to power Meta data centers. AI infrastructure, in other words, is beginning to convert into identifiable nuclear fuel demand — though delivery is still years out.
What has Centrus actually built?
The company completed its first new centrifuge and began shipping equipment from Oak Ridge to Ohio ahead of its annual target. In October it closed the $116 million Westerman acquisition — $95 million in cash, $21 million in stock — tightening control over equipment manufacturing and extending its production chain.
First new centrifuges are expected to run in Ohio in 2029. Centrus plans more than $560 million of investment in its Tennessee facilities. Separately, its American Centrifuge Operating unit won a $900 million US Department of Energy contract to build commercial HALEU capacity at Piketon, Ohio, paid as production milestones are reached. That contract requires one tonne of HALEU by July 2032 and carries two additional five-tonne options.
Where the order book cracks
Roughly $800 million of the Technical Solutions backlog depends on the current HALEU cascade operation contract — and the proposed DOE budget for fiscal 2027 does not include further funding for this activity. The agency has also said it does not currently plan to exercise additional contract options. This is a distinct program from the new $900 million commercial HALEU expansion order; conflating the two would flatter Centrus.
The Piketon lease adds a second, sharper risk. The current lease expires on 1 October 2027. DOE has said it is prepared to discuss a long-term extension until 31 December 2026 — but it is under no obligation to sign one. A failed negotiation would complicate the entire expansion program.
Cash-rich, profit-poor
At the end of September Centrus held $2.236 billion in cash and equivalents, after raising about $500 million gross in September through an equity and warrant offering. Additional warrants could theoretically bring in about $2 billion more — but their strike prices sit in the $227-363 per share range, far above the current quote, so this is not a dependable funding source.
Against that, convertible notes carry a book value of about $1.18 billion, which makes the comparison with a $1.76 billion market capitalization less flattering than it looks at first glance.
Third-quarter operations were weak:
- Revenue fell to $55.5 million from $74.9 million a year earlier
- Gross loss of $10.6 million
- Adjusted net loss of $9.4 million
- GAAP net income of $31.6 million — largely a $46.4 million non-cash warrant liability revaluation plus higher investment income
Nine-month capex reached $226.4 million. Management kept 2026 revenue guidance at $450-500 million, with total capex of $350-500 million excluding Westerman. The money for expansion exists; the open question is deployment efficiency.
Supply obligations complicate the transition
Centrus's purchase obligations under the TENEX contract (the Russian enrichment supplier) may run until 2028, while Russia's decree requiring special export licenses for each shipment remains in force through the end of 2027. The Orano agreement covers supplies through 2030. Centrus must therefore bridge from foreign supply to its own production without breaching existing commitments.
Where does the stock stand technically?
The November candle is incomplete: open $104.74, high $118.29, low $75.91, current close $85.43, month-to-date change of -17.29%. The most-watched support zone is $60-63, where the 61.8% Fibonacci retracement at $60.92, the 100-month moving average at $62.97 and diagonal support converge.
Buyers' immediate task is holding $75.91 and reclaiming $100-105. Next resistance sits at $118-120, with a larger supply zone at $176-200 above it. A break of the November low would raise the odds of a slide toward $60-63 — though even there, technical confluence alone guarantees nothing.
What to watch on 7 December
Centrus holds an Investor Day at the Piketon facility on 7 December. The agenda that matters: expansion timelines, capex, Westerman integration and, above all, lease extension terms. The company has resources and promising agreements. The next step is proving they convert into a working, profitable business — and until deliveries and cash flows replace announcements, the burden of proof stays with Centrus, not with its doubters.
via tradingview.com (Source)
More from Sophie Lindqvist
Show full bio
Correspondent covering money, funding and market shifts around corporate strategy and chief-executive leadership at CEO Frontier.
658 articles
Adjacent sheets
- Oklo Bets on AI Power Hunger With Domestic Nuclear Buildout
- Venture Global Bets on 10 Gigawatts and Global LNG Dominance
- IEA: global oil supply tops demand for first time since Iran war
- Oklo Shares Rebound as Q3 Loss Beats, Analysts Cut Targets
- Nebius Posts 571% Revenue Surge, Yet Stock Falls 8% on Guidance