Field report S-59 / J9 · sheet /expansion

Expansion & MarketsFiled from the territory

Armenia Opens First Commercial AI Data Center as US Faces Backlash

Eleveight AI opened Armenia's first commercial AI data center in June, leaning on a 2025 U.S. memorandum and NVIDIA B300 GPUs as 71% of Americans reject local builds. Experts say scale and latency limit the model.

Grid
S-59 / J9
Surveyed
November 19, 2026
Reading
4 min read
Correspondent
Sophie Lindqvist
As US data centers face increasing backlash, Armenia looks to fill the vacuum
Fig. S-59 / J9As US data centers face increasing backlash, Armenia looks to fill the vacuum — Taken / pixabay

Field notes

  1. 71% of Americans oppose local data center construction; only 7% strongly favor it (March Gallup poll)
  2. Eleveight AI opened Armenia's first commercial AI data center in June, targeting 40 MW
  3. Armenia-U.S. MOU signed by Trump and Pashinyan on Aug. 8, 2025 enabled NVIDIA B300 GPU access
  4. Arakelyan estimates the project's technology split at 90% U.S., 10% other
  5. U.S. hyperscale sites run 300 MW to 1 GW, dwarfing Eleveight's facility

Seventy-one percent of Americans oppose a data center in their area, according to a March Gallup poll, and one Armenian company has decided that statistic is a business opportunity. Eleveight AI opened Armenia's first commercial AI data center in June and is positioning the country as an outsourcing destination for compute that U.S. communities no longer want.

The numbers explain the strategic logic. Only 7% of U.S. respondents told Gallup they "strongly favor" local data center construction, yet demand for computing power keeps climbing. Local legislation restricting new builds has followed, squeezing U.S. tech leaders. Armenia, a small Caucasian country pursuing closer ties with Washington after losing a war to Azerbaijan and watching its relationship with Russia deteriorate, has stepped into the opening.

What does the memorandum change?

Eleveight's operation depends almost entirely on U.S. technology and diplomacy. Chief Business Officer Davit Arakelyan described the project as a "practical implementation" of the Armenia-U.S. memorandum of understanding signed by President Donald Trump and Armenian Prime Minister Nikol Pashinyan on Aug. 8, 2025.

"We are Armenia, we have a border with Iran. If that memorandum would not have taken place, nobody would give us that technology," Arakelyan told the Washington Examiner.

Asked to break down the project by technological importance, Arakelyan estimated "90% U.S., 10% other" — locals built the facility, but U.S. components run from NVIDIA's latest B300 GPUs to Dell-built servers. Co-founder and CEO Arman Aleksanyan credited the MOU with making Armenia "one of the first countries in the world to deploy NVIDIA's latest B300 GPUs."

A State Department spokesperson welcomed the cooperation under the Pax Silica initiative and said the department wants to "build a system that rewards growth and innovation while unleashing American startups, developers and companies to set the pace." The spokesperson added: "We encourage Armenia to select trusted cloud and data center providers as these technologies are the foundation of a prosperous economy and the SI revolution."

Can a 40 MW facility matter?

Scale is the obvious caveat. Aleksanyan said the facility, aiming for 40 megawatts, follows a smaller, sustainable model with a cooling system that uses no drinking water. "We believe our approach offers a viable model for responsible AI infrastructure," he said. "We have not faced the kind of resistance seen around some major U.S. projects, and our environmental choices help explain that."

Bryan Marsh, a 17-year data center industry veteran and former CEO of StratCap's data center division, noted his standard Digital Realty facility from roughly 2009 to 2017 ran about 7 MW — making Eleveight enormous by that era's standards. Today's U.S. hyperscale sites run 300 MW to 1 gigawatt, dwarfing it.

Jonathan Koomey, an independent researcher formerly at Lawrence Berkeley National Laboratory who has studied data centers for over 25 years, framed the viability question around workloads. AI training can run in "batch mode" with little outside communication, making smaller dispersed sites reliable. Serving live customer queries is harder, because latency — the lag between a user's prompt and the reply — grows with distance.

Ivo Ivanov, CEO of DE-CIX, a major internet exchange operator, drew the same line. "For extremely low-latency, real-time applications, such as financial trading and physical AI, compute would need to be located in the same metro area as the users," he said. "For less latency-sensitive use-cases, such as drug discovery or chatbots, compute may be located hundreds of kilometers from the users."

All three experts agreed dispersed facilities will fill niches in a diversified global AI infrastructure network but cannot replace hyperscale campuses. "Such facilities cannot replace the mega-scale campuses for AI training at this stage," Ivanov said. "Both will remain essential to the further development of AI."

What is not said?

The claim of positive Armenian public reception rests on thin evidence. Aleksanyan called the reception "very positive," but no polling exists — data centers are simply too new in the country to measure. Absence of visible discontent is not the same as measured support, and the U.S. backlash took years to organize.

Aleksanyan nonetheless plans to "expand both in Armenia and internationally, carrying forward what we have learned in Gagarin," the facility's site. "I am confident that Armenia will not only maintain but strengthen its position in AI factories, and that this will become one of the most important areas of cooperation between our two countries," he said.

Marsh's assessment is more modest: smaller distributed facilities suit less compute-heavy tasks like IT services, and Eleveight's U.S.-facing focus may carve out niches — not replace the gigawatt campuses that American communities are fighting over.

via washingtonexaminer.com (Source)

Share this article:

More from Sophie Lindqvist

Sophie Lindqvist

Show full bio

Correspondent covering money, funding and market shifts around corporate strategy and chief-executive leadership at CEO Frontier.