Abu Dhabi's 1 GW AI Campus Outstrips the UAE's Power Forecast
Abu Dhabi's 5 GW AI campus would consume 51.7 TWh a year, nearly 30% of UAE 2025 demand, against a 6 TWh national data centre forecast for 2030.
- Grid
- NW-38 / M2
- Surveyed
- November 17, 2026
- Reading
- 5 min read
- Correspondent
- Amara Osei

Field notes
- The full 1 GW Stargate cluster would consume about 10.3 TWh a year; the 5 GW campus would need 51.7 TWh, near 30% of UAE 2025 national demand of 173 TWh.
- Wood Mackenzie forecasts UAE data centre demand at just over 6 TWh by 2030 — less than the 1 GW cluster alone could consume at 70% utilisation (7.2 TWh).
- Partners have committed up to $10 billion for the 1 GW cluster with roughly 100,000 Nvidia GB300 chips; the first 200 MW phase is due live in 2026.
- Taweelah C, a 2.6 GW gas plant backing the cluster, is not expected to commission until late 2028; a 5.2 GW solar-plus-19 GWh battery project closed at $6.1 billion in July 2026.
- Khazna holds about 60% of UAE commercial wholesale capacity with a 1,000 MW pipeline target; Stargate phase 1 would absorb a fifth of it.
Abu Dhabi's flagship AI campus is designed to consume up to 51.7 TWh of electricity a year — close to 30% of the UAE's entire 2025 national demand of 173 TWh — according to conversions of published capacity figures as of November 2026. The number sits awkwardly beside the country's own planning forecast, which puts all UAE data centre consumption at just over 6 TWh by 2030.
The first 200 MW of Stargate UAE, a cluster built by G42 through its subsidiary Khazna and operated with OpenAI and Oracle, is due to go live this year inside a 26 square kilometre campus in Abu Dhabi. The partners have pegged investment at up to $10 billion for a 1 GW cluster fitted with roughly 100,000 Nvidia Grace Blackwell GB300 chips, announced in May 2025.
How much power does 200 MW actually mean?
TrendForce estimated that a GB300 system with 72 chips draws about 140 kW. At that rate, the 100,000 chips work out to roughly 1,400 systems and about 196 MW of IT load, which is why the partners settled on 200 MW for the first phase in 2026.
Modern desert builds in the UAE are designed at a power usage effectiveness (the ratio of total facility energy to IT energy) of about 1.18, so 200 MW of chips becomes roughly 236 MW at the fence line. Run flat out for a year, the phase consumes about 2.1 TWh.
For context, Wood Mackenzie estimated that every data centre in the UAE consumed about 3 TWh in 2025, roughly 2% of national demand. The full 1 GW Stargate cluster becomes 1.18 GW at the fence and about 10.3 TWh a year. The 5 GW campus announced in 2025 becomes 5.9 GW and about 51.7 TWh annually.
These are ceilings, not forecasts. At 70% utilisation the 1 GW cluster still needs about 7.2 TWh a year; at 50% it needs 5.2 TWh — nearly as much as the 6 TWh the whole national data centre estate is projected to consume in 2030.
Why do the two forecasts disagree?
In March 2026, Wood Mackenzie put UAE data centre demand at just over 6 TWh by 2030, and EWEC, the Abu Dhabi utility that procures the emirate's power and water, has used a similar figure. That forecast was built on colocation demand — racks rented by banks, telcos and cloud regions — not on a single tenant whose load arrives in 200 MW blocks.
The gap has not been published: how much of Stargate's 1 GW is inside the 6 TWh figure, and how much sits on top. Khazna, which holds about 60% of the UAE's commercial wholesale capacity and targets a 1,000 MW pipeline, is both landlord for the national market and contractor for the campus. Stargate's first phase would absorb a fifth of that pipeline target.
Larry Ellison, Oracle's chief technology officer, said at launch: "This first-in-the-world platform will enable every UAE government agency and commercial institution to connect their data to the world's most advanced AI models." That is a statement about demand, not supply.
Can the grid deliver firm power?
Abu Dhabi holds the Middle East's only operating nuclear fleet. Barakah supplies about 21% of UAE electricity output, with 4,170 MW in service and another 1,390 MW to come. Solar contributed about 9% of generation in 2025, projected above 20% by 2040.
Neither solves the problem alone: nuclear runs flat, and solar stops at sunset. The procurement list filling the gap:
- Taweelah C, a 2.6 GW combined cycle gas plant with Siemens Energy turbines, led by TAQA with Al Jomaih and Sembcorp, commissioning expected in late 2028.
- A Masdar-EWEC round-the-clock renewable project pairing 5.2 GW of solar with 19 GWh of batteries for 1 GW of firm output; financial close came in July 2026 at about $6.1 billion, with operations targeted for 2027.
- Barakah's remaining nuclear units.
The arithmetic is tight. Nineteen gigawatt hours of storage equals 19 hours of delivery at full rate — enough for a night, not a week of dust or a gas outage. Taweelah C, at a 60% capacity factor, would produce about 13.7 TWh a year from 2029, more than the full Stargate cluster needs.
What does the campus buy before chips?
G42 said in October 2025 that civil, structural and mechanical work was ahead of schedule and all long-lead equipment had been procured. A design PUE of 1.18 in a desert climate implies rack-level liquid cooling and closed-loop heat rejection. In the 2026 phase, the first $1 billion goes to switchgear, transformers, cooling and construction; chips arrive last.
The project also reflects politics. The Trump administration rescinded Biden-era AI chip export restrictions in 2025 and set up a bilateral Commerce Department working group; the UAE committed reciprocal investment in US AI infrastructure. Microsoft's September 2025 export licence authorised 60,400 A100-equivalent units on top of 21,500 already deployed. Microsoft's cumulative UAE commitment has reached $15.2 billion, and AWS has committed $1 billion with e&.
Khazna, with 400 MW of colocation capacity recorded in 2026, can price scarcity: tenants needing 2027 capacity negotiate against a queue. RAX puts the UAE colocation market at $1.39 billion in 2026, rising to $3.90 billion by 2030 at 21.7% CAGR — a forecast that does not model a single 1 GW tenant. The UAE hosts 19 international submarine cables with 99.5% fibre-to-the-home coverage in 2024.
The UAE has also promised ChatGPT Plus, listed at $20 a month, free to all citizens and residents — the first country to do so. The risk sits in sequencing: Taweelah C commissions in late 2028, the battery project targets 2027, and the first 200 MW is meant to be live this year.
via itbusinessnet.com (Source)