Field report SE-24 / Q1 · sheet /expansion
Expansion & MarketsFiled from the territory
Ucore Secures Louisiana Air Permit for 9,600-Tonne Rare Earth Complex
Ucore Rare Metals has received LDEQ Air Permit No. 2360-00177-00, clearing construction of its Alexandria SMC through full 9,600 tpa build-out and enhanced Machine A commissioning in H1 2027.
- Grid
- SE-24 / Q1
- Surveyed
- November 18, 2026
- Reading
- 3 min read
- Correspondent
- Amara Osei

Field notes
- Ucore received Air Permit No. 2360-00177-00 from the LDEQ on November 17, 2026.
- The permit covers SMC construction through full build-out at approximately 9,600 tpa of contained TREO.
- Enhanced Machine A, the first 600 tpa of TREO capacity, is scheduled for commissioning in H1 2027.
- The Air Permit is the final LDEQ permit required before enhanced Machine A installation.
- Ucore trades as UCU on the TSXV and UURAF on the OTCQX market.
Ucore Rare Metals Inc. (TSXV: UCU; OTCQX: UURAF) has received its Minor Source Air Permit (Permit No. 2360-00177-00) from the Louisiana Department of Environmental Quality (LDEQ), covering construction through full build-out of the company's Strategic Metals Complex (SMC) at up to approximately 9,600 tonnes per annum (tpa) of contained total rare earth oxide (TREO).
The company announced the permit, dated November 17, 2026, from Halifax, Nova Scotia. The LDEQ approved the permit for the construction, testing, commissioning and operation of the SMC in Alexandria, Louisiana, from the initial enhanced 'Machine A' through the planned full commercial scale.
What does the permit actually cover?
The application rested on processing metrics drawn from tonnes of mixed rare earth carbonate (MREC) and mixed rare earth oxide (MREO) feedstocks processed at Ucore's RapidSX Commercialization and Demonstration Facility (CDF) in Kingston, Ontario. RapidSX is Ucore's proprietary rare earth separation technology.
A minor source permit in Louisiana applies to facilities whose potential emissions fall below the thresholds requiring a federal Title V (Part 70) operating permit. The 'Minor Source' label describes the facility's emissions category, not its physical size or processing capacity.
The Air Permit is the final LDEQ permit required before enhanced Machine A can be installed, using full-commercial-scale RapidSX construction details developed at the Kingston CDF. That facility has completed automated contactor column testing at commercial dimensions: two 8-inch columns (enhanced Machine A), four 12-inch columns and one 24-inch column.
What did management say?
Mike Schrider, P.E., Ucore's Vice President and Chief Operating Officer, credited the state regulator for the pace of the process. He said: "Ucore is very appreciative of the LDEQ and the State of Louisiana for facilitating an efficient permitting process based on our extensive demonstration work at the CDF."
Schrider added: "With the Air Permit in hand and regular coordination with the State Fire Marshal and the England Airpark, Ucore continues detailed engineering and construction of an advanced-technology separation facility. This facility, starting with enhanced Machine A, will process feedstock from multiple Western sources into a wide range of separated products, including NdPr, samarium, gadolinium, and yttrium, for the United States, Canada, and their allies."
NdPr (neodymium-praseodymium) is the rare earth pairing used primarily in permanent magnets. Samarium, gadolinium and yttrium are medium and heavy rare earths used in defense, medical and electronics applications.
Schrider framed the milestone within the project timeline: "Each Company milestone achieved is a building block toward commissioning enhanced Machine A in the first half of 2027 and, beyond that, supplying medium and heavy rare earth oxides to Western markets."
What comes next?
Ucore's immediate focus is installing, testing and commissioning the first 600 tpa of TREO processing capacity, enhanced Machine A, in the first half of 2027. The 9,600 tpa figure represents the planned full build-out of the complex.
The Alexandria facility is the first in a planned sequence. Ucore intends to develop subsequent SMCs in Canada and Alaska, and longer term to advance its 100% controlled Bokan-Dotson Ridge Rare Heavy REE Project on Prince of Wales Island in Southeast Alaska.
The company says the Louisiana complex, alongside strategic partnerships, supports a more diversified North American rare earth elements (REE) supply chain. Ucore is listed on the TSXV under 'UCU' and on the OTCQX Best Market under 'UURAF'.
The company's forward-looking statements carry standard caveats: permit scope and continued validity, the timing of remaining approvals, the H1 2027 commissioning schedule, the scale-up to roughly 9,600 tpa and future supply of medium and heavy rare earth oxides all depend on assumptions that may not hold. Risks cited include permitting challenges, financing conditions, feedstock variability, rare earth oxide price volatility and the possibility that RapidSX may not perform at commercial scale as demonstrated.
via itbusinessnet.com (Source)
More from Amara Osei
Show full bio
Market editor covering people, launches and day-to-day practice in corporate strategy and chief-executive leadership at CEO Frontier.
452 articles
Adjacent sheets
- Nigeria to Licence Scrap Metal Dealers in 2026 Crackdown on Cable Theft
- EnergyX Bets $2 Billion Trafigura Deal Proves Lithium's Fast Track
- Nigeria Moves to Regulate Scrap Metal Trade to Stop Infrastructure Vandalism
- Galantas Gold locks in a Chile buyer and a $10 million line
- India bans lithium-ion battery black mass exports to retain feedstock