Afentra Targets 2027 Restart at Angola's Quenguela Norte Field
Afentra plans to revive the Quenguela Norte field onshore Angola via a four-well pilot targeting first oil in H2 2027, while Impala-2 offshore flows from January at 4,000 bpd.
- Grid
- SW-12 / M4
- Surveyed
- November 20, 2026
- Reading
- 3 min read
- Correspondent
- Olivia Hart

Field notes
- Afentra targets first production from the Quenguela Norte pilot in the second half of 2027 via re-entry of four legacy wells.
- KON 15 leads could hold up to 350 million barrels of unrisked oil in place; 300 km of 2D seismic is planned for Q1 next year.
- Sonangol spudded Impala-2 in Block 3/05; first oil expected January 2027 at 4,000 bpd, with costs capped at $60 million.
- Pacassa SW remapping is expected to confirm up to 70 million barrels of incremental resources, matching pre-drill estimates.
- A final investment decision on the Golungo-Palanca-Quissama complex in Block 3/24 is targeted for H1 next year.
Afentra plans to restart oil production at the Quenguela Norte field onshore Angola in the second half of 2027, reviving an asset shut in since 1999 during the country's civil war. The UK-listed junior set out the timeline in an operational and financial update on Tuesday, placing a low-cost pilot development at the centre of its Kwanza basin strategy.
The pilot scheme involves re-entering four existing wells in Block KON 4. Afentra frames it as a way to prove the concept for a phased redevelopment of Quenguela Norte while holding down initial capital investment.
What does the pilot change for Afentra?
The re-entry approach converts a dormant legacy asset into a near-term production option without the cost of a full redevelopment. For a company built on acquiring mature assets in West Africa, the pilot offers a template it could repeat across the basin if the four wells deliver.
Chief executive Paul McDade said: "We are focused on building a low-cost position across the Kwanza basin, with work underway to assess a potential production pilot at the Quenguela Norte field, including the re-entry of legacy wells delivering production in the second half of 2027."
Elsewhere in KON 4, Afentra has identified a number of Tertiary-age leads next to Quenguela Norte. A focused 2D seismic programme around the field is being evaluated for the first half of 2027 to define structures better and support future drilling decisions.
How big is the onshore prize?
In neighbouring KON 15, where Afentra has mapped pre-salt and post-salt leads, the company plans to acquire 300 kilometres of 2D seismic in the first quarter of next year. That campaign feeds a goal of drilling the block's first exploration well in 2028.
Afentra estimates the targets on KON 15 could host up to 350 million barrels of unrisked oil in place, according to internal estimates. To put that scale in perspective, it dwarfs the near-term production volumes Afentra is chasing offshore — the Impala-2 well will start at 4,000 barrels per day.
A seismic campaign is also lined up for block KON 19 next year.
What is happening offshore?
At sea, Sonangol has spudded the Impala-2 development well in Block 3/05, with first oil expected in January 2027 at an initial 4,000 barrels per day. The partners chose to fund the well directly rather than through a previously agreed carry mechanism. Impala-2's cost is capped at $60 million.
Afentra said the direct funding route lets it participate in production revenues from first oil and capture the full capital expenditure uplift available under the block's production sharing contract.
After Impala-2 is complete, the Borr Grid jackup will drill a sidetrack at the Pacassa SW oil discovery, also in Block 3/05. First oil from Pacassa SW is now expected at the end of the first quarter of 2027, tied back to the existing Pacassa production infrastructure.
How large is Pacassa SW?
Remapping of Pacassa SW continues as Afentra incorporates the discovery well results. The company expects this work to confirm significant incremental oil resources of up to 70 million barrels, matching pre-drill expectations.
That confirmation matters for the wider block, because it would firm up the resource base behind future development decisions in 3/05.
What comes next in Block 3/24?
In adjacent Block 3/24, work continues on a phased development plan for the Golungo-Palanca-Quissama complex. Afentra targets a final investment decision in the first half of next year.
Afentra is an independent oil and gas company focused on acquiring and developing mature, producing assets in West Africa. Its portfolio spans production, near-field development and exploration assets in Angola.
via euro-petrole.com (Source)
More from Olivia Hart
Show full bio
News editor covering regulation, policy and their impact on corporate strategy and chief-executive leadership at CEO Frontier.
474 articles
Adjacent sheets
- Afreximbank's $2bn Facility Targets Cross River's Project Pipeline
- QatarEnergy Buys 25% of Chevron-Operated Block Offshore Namibia
- Absa accelerates African expansion despite Kenya ownership shortfall
- Barbados $32m Medicine Plant Advances; 2029 Still Conditional
- Nigeria's Active Drilling Rigs Up Over 300% From 2021 — NUPRC